- Embedded Buffer Charts now include the Warning Score just the same as on the Power BI buffer chart and Milestone Status Report.
- Warning Score is a measure of confidence in the buffer chart’s current accuracy.
- Higher score → lower confidence
- Lower score → higher confidence
- Warning Score = sum of points assigned for out-of-date, unassigned, and unlinked tasks related to the Tracking Milestone.
- 1 point/unlinked task
- 1 point/unassigned task
- 1 point/OOD (Active & Planned)
- Points for the Max OOD Active task
- Points for the Max OOD Planned task
- When you hover over the Warning Score, a tooltip shows the tasks contributing to it with the Critical & Near-Critical tasks displayed at the top.
- Active (in-work), Out of Date (OOD) - # days
- Planned (backlog), OOD - # days
- Unassigned
- Unlinked
- Warning Score is a measure of confidence in the buffer chart’s current accuracy.
-
-
- The Tracking Milestone tooltip has been improved.
- Reporting Date is included
- Impact Reasons wrap text
- Embedded buffer charts can also now be opened from the Milestone Status view via a right-click on the buffer, then clicking Show Chart.